It's been 20 days since I have posted anything here. That's only because there's nothing really we could do while waiting for paperwork to be done by my builder. He was organising for the 5 Star energy rating to be completed with the architect and builder engineers, permits approval from the Town Council, etc. HOWEVER, we have progress!!!! (.... was beginning to have Home Building withdrawal symptoms!)
Progress Report from My Builder
- Site cut has been completed (pictures to come soon! woke up at 6.45am just to drive down to the land to take pictures this morning!)
- Architecturals are completed, awaiting Reflections Estate to sign off (should have them back by tomorrow)
- Engineering plans completed (although I would wish to take a look at them)
- 5 star energy rating completed
- Property info completed
- Applied for PIC (Property Identification Code) number (awaiting response) - this I am not entirely sure if my property actually needs a PIC Number! Will check with builder what this means...
- Building permit (awaiting Estate's signoff of plans)
- Block to be pegged out by Friday *he hopes*